Learning Center · Laws and permits

How Net Metering Works in the Philippines

Net metering lets you connect a solar system of up to 100 kW to your electric company’s grid, send out the power you do not use, and get a credit on your bill. Credits can be banked, and the DU paperwork is down to four items. The catch: exports are credited at the DU’s blended generation cost, not the full retail rate, so using your own solar power directly saves more than exporting it. Many DIY builds skip net metering and go zero-export instead.

Updated November 22, 2026 · Rules checked November 22, 2026 · By the SunTipid team · Not legal advice

Size cap100 kWRenewable systems in the program
LGU permit3 working daysThen deemed approved
LGU inspection (CFEI)7 working daysThen deemed approved
DU processing10 working daysFor the interconnection

What is net metering?

Net metering is a program created by the Renewable Energy Act of 2008 (RA 9513, Section 10). If you own a renewable energy system, such as rooftop solar, you connect it to the grid of your distribution utility (DU). The DU is your electric company, like Meralco or your local electric cooperative. When your panels make more power than your house is using, the extra goes out to the grid. When your panels make less, you pull power from the grid as usual. At the end of the month, the DU credits what you sent out against what you took in.

About 21,224 customers were enrolled as of December 2025: 17,141 in Luzon, 3,179 in the Visayas and 904 in Mindanao.

How does net metering work, step by step?

  1. Design the system. Size it with the SunTipid Builder and have the plans checked by a licensed electrical engineer if your LGU requires it.
  2. Get the LGU electrical permit. Your city or municipality has 3 working days to act on it.
  3. Install, then get the CFEI. After a final inspection, your LGU issues the certificate of final electrical inspection, which it must do within 7 working days.
  4. Submit your four DU items. See the list below.
  5. The DU approves and connects you. The DU has 10 working days to process the interconnection. It also sets up the metering so your imports and exports are counted.
  6. Your bill shows the credit. Exports are credited against your bill and unused credits carry over.

The order above is the usual one. Your DU may ask for steps in a slightly different order, so check its published net-metering page first.

What are the net-metering rules in 2026?

The Energy Regulatory Commission (ERC) rewrote the rules in 2025 to make net metering easier. Here is what matters for a home owner.

RuleWhat it saysSource
System sizeRenewable energy systems up to 100 kW can join the program.RA 9513 and ERC net-metering rules
Export creditExported power is credited at the DU’s blended generation cost, not the full retail rate.Net-metering rules, checked against official summaries and news coverage (Nov 2026)
Banking creditsUnused credits can be banked and rolled over to future bills.ERC Resolution No. 15, s. 2025
Selling the houseCredits can transfer to the new owner with a conforme letter from the original owner.ERC Resolution No. 15, s. 2025
REC meterA separate renewable energy certificate (REC) meter is now voluntary. If you skip it, you file an affidavit and output is computed by formula.ERC Resolution No. 15, s. 2025, Sec. 19
Online processDUs must publish their forms, accept applications online, and post hosting capacity per transformer every quarter.ERC Resolution No. 15, s. 2025
RECs and multi-siteThe owner keeps the RECs. Several sites under the same DU franchise can be netted together.DOE supplemental policy, Oct 2025

How long does net-metering approval take?

A 2026 joint circular from the Department of Energy, DILG and DPWH tells LGUs to act fast. If they miss the deadline, your application is treated as deemed approved. It also says LGUs should not add extra requirements, and a barangay clearance is generally not needed.

StepWhoTime limit
Electrical permitYour city or municipality (LGU)3 working days, then deemed approved
Certificate of final electrical inspection (CFEI)Your LGU7 working days, then deemed approved
Interconnection and net-metering approvalYour DU (Meralco, coop, etc.)10 working days

The 10 working day DU limit comes from a DOE directive under Executive Order 110 (the energy emergency). The normal limit is 20 working days, so it may go back to 20 if the emergency ends.

These are legal limits, not guarantees. Allow extra time for corrections and for your installer’s schedule.

What paperwork do you need for the DU?

Since the ERC advisory of September 22, 2025, the DU’s paperwork is cut down to four items:

  1. COC application form. The ERC certificate of compliance form, which your DU can help you file.
  2. CFEI from your LGU. The certificate of final electrical inspection.
  3. The amended net-metering agreement with your DU. No notarization is needed and e-signatures are accepted.
  4. The COC fee.

Your installer usually files these for you. If you are going DIY, ask your DU for its online net-metering form first.

How much is exported power worth?

Less than most people expect. Exported power is credited at the DU’s blended generation cost, which is only part of what you pay per kWh. Your retail rate also includes transmission, distribution, taxes and other charges. For example, Meralco’s residential rate in November 2026 was about ₱15.55 per kWh at 200 kWh of use, and the credit you earn for exports is lower than that.

What this means for your design. Use as much of your solar power as you can yourself, in the daytime or through a battery. Every kWh you use directly saves the full retail rate. Every kWh you export earns less. That is why the SunTipid Builder sizes your system to your own use and does not count on export income.

Net metering vs zero-export vs micro-solar

In August 2026 the DOE issued Department Circular DC2026-08-0017, which created two simpler paths for own-use solar. For most DIY homes, one of them fits better than net metering.

Net meteringZero-exportMicro-solar (up to 1 kW)
What it isGrid-tied, exports extra power for a bill creditOwn use only. Grid-tied with an export limiter, or fully off-gridPlug-and-play kit, up to 1,000 W of panels and 800 W micro-inverter
Agreement with DUYes, net-metering agreementNotice to the DU if grid-tied. None if off-gridWritten notice to the DU after installing
ERC certificate of complianceYesWaived for householdsNo
PermitsLGU electrical permit and CFEIBuilding permit, unless your LGU confirms your existing permit covers it. Installation must follow the Philippine Electrical Code (PEC)No building permit
Pays you for exportsYes, at blended generation costNo. Exports earn nothingNo
Best forHomes that use little power in the daytime and want credit for the restMost DIY builds, with or without a batteryVery small loads like a fan, lights and chargers
Heads up: if you export power without a net-metering agreement, that power earns nothing. If you want zero-export, your system needs an export limiter, or it must be fully off-grid.

Do you need net metering?

Net metering makes sense if:

  • You are away from home most of the day, so your panels make more than you use.
  • You want a bigger array than your own use needs, and are happy with a lower export credit.
  • You plan to net several sites under the same DU franchise.

Zero-export or off-grid is simpler if:

  • You use most of your power in the daytime, such as with aircon, a work-from-home setup or a home business.
  • You are adding a battery for backup and want to skip the ERC certificate of compliance and DU agreement.
  • You want the lightest paperwork possible.

Whichever you choose, the Philippine Electrical Code (PEC 2017, Article 6.90 for solar PV) and your LGU’s electrical permit rules still apply. Net metering does not skip the engineering.

Not sure what size you need? Start from your bill: ₱5,000, ₱8,000, ₱10,000, ₱15,000 or ₱20,000 a month.

Frequently asked questions

What is net metering in the Philippines?

Net metering is a program under the Renewable Energy Act (RA 9513, Section 10). It lets a customer with a renewable energy system of up to 100 kW connect to the electric company’s (distribution utility, or DU) grid, send out the power they do not use, and get a credit on their bill.

Is exported solar power paid at the same rate I pay for electricity?

No. Under the net-metering rules we verified, exported power is credited at the DU’s blended generation cost, which is lower than the full retail rate you pay per kWh. That is why using your solar power directly in the daytime saves more than exporting it.

How long does net-metering approval take?

The national rules set a 3 working day limit for the LGU electrical permit and 7 working days for the LGU certificate of final electrical inspection (CFEI), or the application is treated as deemed approved. The DU then has 10 working days to process the interconnection under the current emergency directive (normally 20). Real timelines vary, so treat these as limits, not promises.

Do I need net metering if I want to avoid Meralco bills?

Not necessarily. If you size your system to use what you make (with or without a battery) and block exports, a zero-export system under DOE Department Circular DC2026-08-0017 does not need an ERC certificate of compliance for households. You only need net metering if you want credit for power you send to the grid.

Do I still need a licensed engineer if I use net metering?

Yes. Net metering does not replace the Philippine Electrical Code, the electrical permit or a professional electrical engineer’s signed plans for larger systems. Ask your LGU what size triggers a PEE seal, since practice differs by city.

Can I bank net-metering credits or move them to a new owner?

Under ERC Resolution No. 15, series of 2025, credits can be banked and rolled over to future bills, and they can transfer to a new owner when the property is sold, with a conforme letter from the original owner.

Ready to size your own system?

Pick your bill, see the parts, and decide if you want to export or keep it zero-export.

Build my setupRead the solar laws

Sources and last checked

Checked November 22, 2026. SunTipid is not a law firm and this is not legal advice. Confirm details with your DU and LGU before you buy or install.

  • Renewable Energy Act of 2008 (RA 9513), Section 10.
  • ERC Resolution No. 15, series of 2025, 2025 Amended Rules Enabling the Net-Metering Program for Renewable Energy. News coverage: GMA News, Inquirer.
  • DOE-DILG-DPWH joint memorandum circular on LGU permits. Coverage: Power Philippines.
  • DOE Department Circular DC2026-08-0017 on zero-export and micro-solar systems. Coverage: GMA News.
  • Meralco residential rate, November 2026, from company.meralco.com.ph.
  • The official text of DOE Department Circular DC2026-08-0017, read on the DOE website.